Mahira Homes:- Construction Work Status (February 2023)
S.No. Towers Current Status 
1 Tower A Tile Work  - 95%
Internal Paint  - 60%,
External Paint 1st Coat  -100%
Door Frame Fixing - 100%
Door Shutter Fixing - 90%
Glass Fixing - 100% 
2 Tower B Tile Work  - 95%
Internal Paint  - 60%,
External Paint 1st Coat  -100%
Door Frame Fixing - 100%
Door Shutter Fixing - 90%
Glass Fixing - 100% 
3 Tower C Tile Work  - 95%
Internal Paint  - 60%,
External Paint 1st Coat  -95%
Plumbing Work - 100%
Door Frame Fixing - 100%
Door Shutter Fixing - 90%
Glass Fixing - 100% 
4 Tower D Tile Work  - 95%
Internal Paint  - 60%,
Door Frame Fixing - 100%
External Paint 1st Coat  - 100%
Plumbing Work - 100%
Glass Fixing - 100% 
5 Tower E Tile Work  - 70%
Internal Paint  - 60%,
Door Frame Fixing - 80%
External Paint 1st Coat  - 100%
Plumbing Work - 100%
6 Tower F Tile Work  - 60%
Internal Paint  - 50%,
Door Frame Fixing - 100%
External Paint 1st Coat  - 60%
Plumbing Work - 100%
7 Tower G Parapet & machine room work in progress  (Structure)  - 70%
Internal (1st coat putty)  external Paint(primer) in progress - 80%
8 Tower H Ground to 1st floor work is stable (Structural) 
9 Tower J Up to plinth beam level work only completed(Structural) 
10 Tower L 4th floor level slab in progress  (Structural)
11 Tower M 11th floor level slab in progress  (Structural) 
12 Tower N 5th floor level slab in progress  (Structural) 
13 External Development Sewer Line 50% completed Boundary wall work stable
14 STP Raft foundation casted 50% 