mahira-homes-68

MAHIRA HOMES 68

S.N Tower- ID Activities Status as on 11-Oct-21
1 Tower- A Railing Balcony/Staircase (KG) Completed
staircase Hand Rail (KG) In progress
Plumbing (Flat) Completed
Water proofing (Floor) Completed
AAC Block,Brick work & Plaster   AAC block work Completed
Door Frame (Flat) Completed,Except Ground Floor
Wall Tile (Sq ft) Completed,Except Ground Floor
Floor Tile (Sq ft) Completed,Except Ground Floor
External paint  1st Coat Com pelted
Internal paint  1st coat putty Completed 
Lift (No.) Work in Progress
2 Tower- B Railing Balcony/Staircase (KG) Completed
staircase Hand Rail (KG)  
Plumbing (Flat) Completed
Water proofing (Floor) Completed
AAC Block,Brick work & Plaster   Completed
Door Frame (Flat) Completed
Wall Tile (Sq ft) Completed,Except 1st Floor
Floor Tile (Sq ft) Completed,Except 1st Floor
External paint (Sq ft) In progress
Internal paint (Sq ft) 1st coat putty Completed 
Lift (No.) Work in Progress
Railing Balcony/Staircase (KG) Completed
staircase Hand Rail (KG) Completed
3 Tower- C Plumbing (Flat) Completed
Water proofing (Floor) Completed
AAC Block,Brick work & Plaster   Brick work complete
Door Frame (Flat) Completed 
External paint (sq ft) IN progress
4 Tower- D    
Railing Balcony/Staircase (KG) Completed
staircase Hand Rail (KG) Completed
Plumbing (Flat) Completed
Water proofing (Floor) 10th Floor in progress
AAC Block work (DB) To be started 
  Wall tile in toilet 13th Floor Completed 
    Floor tile 5th Floor in progress
    Lift Block work Block work Completed
4 Tower- E    
Railing Balcony/Staircase (KG) Completed
staircase Hand Rail (KG) Work in Progress
Door frame  Partially Completed 
Plumbing (Flat) Completed 
Water proofing (Floor) Completed 
AAC Block work (DB) To be started 
  Wall tile in toilet 9th Floor Completed 
    Floor tile 4th Floor in Progress
    Lift Block work Block work Completed
       
6 Tower- F Railing Balcony/Staircase (KG) Completed 
staircase Hand Rail (KG) Work in Progress
    Plumbing Completed up to 13th Floor 
    Door Frame Partially Completed 
7   Structure Activities  
Tower-G Structural slab 10th  Floor lvl 1st pour casting  in progress
8 Tower-H Column  Column completed up to plinth beam bottom and plinth beam work in progress
  Tower-J Column  Column40% casting Completed and balance in progress
9 Tower-L Slab 1st Floor lvl pour-01 Completed and 2nd pour slab column steel in progress
10 Tower-M Slab 8th Floor slab pour-01 Completed and 2nd in progress
11 Tower-N Slab 2nd pour -01 shuttering complete and 2nd column steel in progress 