MAHIRA HOMES 68
S.No.
TOWER
WORK DESCRIPTION
PROGRESS IN%
(As of 04 April 2022)
1
Tile Work
98%
Internal Paint
20%
TOWER-A
External Paint 1
st
Coat
100%
Door Frame Fixing
100%
Door Shutter Fixing
90%
Glass Fixing
100%
2
Tile Work
98%
Internal Paint
20%
TOWER-B
External Paint 1
st
Coat
100%
Door Frame Fixing
100%
Door Shutter Fixing
90%
Glass Fixing
100%
3
Tile Work
95%
Internal Paint
20%
TOWER-C
External Paint 1
st
Coat
95%
Plumbing Work
100%
Door Frame fixing
100%
Door Shutter Fixing
90%
Glass Fixing
100%
4
Tile Work
95%
Internal Paint
20%
TOWER-D
Door Frame fixing
100%
External Paint 1
st
Coat
100%
Plumbing Work
100%
Glass Fixing
100%
5
Tile Work
70%
Internal Paint
20%
TOWER-E
Door Frame fixing
70%
External Paint 1
st
Coat
100%
Plumbing Work
100%
6
Tile Work
40%
Internal Paint
20%
TOWER-F
Door Frame fixing
100%
External Paint 1
st
Coat
60%
Plumbing Work
100%
7
TOWER-G
Terrace level slab completed (Structure)
8
TOWER-H
Ground to 1
st
floor in Progress (Structural)
9
TOWER-J
Plinth beam in progress (Structural)
10
TOWER-L
5th floor level slab in progress (Structural)
11
TOWER-M
12
th
floor level slab in progress (Structural)
12
TOWER-N
6th floor level slab in progress (Structural)
More Construction Update
Mahira Homes 103
Mahira Homes 95
Mahira Homes 63A
BECOME AN
ASSOCIATE
Name
Phone
Please Wait...
Quick inquiry
Top
Quick inquiry
Mahira Homes will contact you within 24 working hours to understand your requirements.
I am interested in
Select Project
MAHIRA HOMES 95
MAHIRA HOMES 68
MAHIRA HOMES 63A
MAHIRA HOMES 104
MAHIRA HOMES 103
Name
Email
Phone
Message
Please Wait...