Mahira
Homes:- Construction Work Status (February 2023) |
S.No. |
Towers |
Current Status |
1 |
Tower A |
Tile Work - 95%
Internal Paint - 60%,
External Paint 1st Coat -100%
Door Frame Fixing - 100%
Door Shutter Fixing - 90%
Glass Fixing - 100% |
2 |
Tower B |
Tile Work - 95%
Internal Paint - 60%,
External Paint 1st Coat -100%
Door Frame Fixing - 100%
Door Shutter Fixing - 90%
Glass Fixing - 100% |
3 |
Tower C |
Tile Work - 95%
Internal Paint - 60%,
External Paint 1st Coat -95%
Plumbing Work - 100%
Door Frame Fixing - 100%
Door Shutter Fixing - 90%
Glass Fixing - 100% |
4 |
Tower D |
Tile Work - 95%
Internal Paint - 60%,
Door Frame Fixing - 100%
External Paint 1st Coat - 100%
Plumbing Work - 100%
Glass Fixing - 100% |
5 |
Tower E |
Tile Work - 70%
Internal Paint - 60%,
Door Frame Fixing - 80%
External Paint 1st Coat - 100%
Plumbing Work - 100% |
6 |
Tower F |
Tile Work - 60%
Internal Paint - 50%,
Door Frame Fixing - 100%
External Paint 1st Coat - 60%
Plumbing Work - 100% |
7 |
Tower G |
Parapet & machine room work
in progress (Structure) - 70%
Internal (1st coat putty) external
Paint(primer) in progress - 80% |
8 |
Tower H |
Ground to 1st floor work is
stable (Structural) |
9 |
Tower J |
Up to plinth beam level work
only completed(Structural) |
10 |
Tower L |
4th floor level slab in
progress (Structural) |
11 |
Tower M |
11th floor level slab in
progress (Structural) |
12 |
Tower N |
5th floor level slab in
progress (Structural) |
13 |
External Development |
Sewer Line 50% completed
Boundary wall work stable |
14 |
STP |
Raft foundation casted 50% |